How much does a structure-only build cost in Riyadh?
The structure rate per square metre with materials and labour, what it covers and leaves out, and a table for 200 to 1,000 m². The figures come from the Kamyeklaf calculator engine itself, from published Saudi references for 2026, and they are planning estimates, not a contractor quote.
The short answer
The structure of an ordinary new villa in Riyadh costs about SAR 550 – 750/m² with materials and labour. A villa with 400 m² of built area (all floors, not the plot) has a structure of about SAR 220k – 300k, which is about 35% of a full build at the standard level; the rest is finishing. The low end is an economical contractor and a simple plan, the high end a pricier contractor or a design with wide spans and projections.
Structure cost by size
Built area
Structure with materials and labour
Rate per m²
200 m²
SAR 110k – 150k
SAR 550 – 750/m²
300 m²
SAR 165k – 225k
SAR 550 – 750/m²
400 m²
SAR 220k – 300k
SAR 550 – 750/m²
500 m²
SAR 275k – 375k
SAR 550 – 750/m²
600 m²
SAR 330k – 450k
SAR 550 – 750/m²
800 m²
SAR 440k – 600k
SAR 550 – 750/m²
1000 m²
SAR 550k – 750k
SAR 550 – 750/m²
The area is the total built area of all floors including the roof annex, not the plot. The figures are for a new villa with an ordinary concrete frame and block masonry, and exclude the basement, the boundary wall, outdoor works, finishing and VAT.
The rate per metre is flat in this index because the published reference gives a price per metre, not per building. In real quotes the structure rate tends to fall on large villas with a regular plan and rise on small or complex ones, because formwork, equipment and site setup do not scale with area.
What does the structure price cover?
Excavation and foundationsOrdinary excavation to foundation depth, blinding concrete, footings, necks and ground beams, and backfill. Rock or deep excavation and weak soil are priced separately by a dedicated quote.
The concrete frameColumns, beams, slabs, stairs, the roof tank and the annex roof, with steel, concrete and formwork, up to the last slab of the building.
MasonryExternal and internal block walls with mortar, plus lintels over openings. This is the point at which the “structure” is handed over in most contracts.
Materials and labourThe figures here are for an all-in quote in which the contractor supplies steel, cement, blocks and timber and provides the labour. A labour-only quote is a lower figure, but the materials are bought at your expense.
What does it leave out?
The difference between two structure quotes is usually about scope, not price. These items are outside the figures in this guide; some contractors add them to a structure quote and some do not:
Plaster and insulationInternal and external plaster, roof waterproofing and thermal insulation, and bathroom waterproofing. In the Saudi market these usually count as finishing, and the calculator counts them that way. Some structure quotes include roof insulation or façade plaster; ask.
First-fix servicesElectrical, plumbing and air-conditioning conduits inside the concrete and walls before plastering. Many structure contracts include only the empty conduits in the slabs and leave the full first-fix to the finishing stage.
Basement and special excavationA basement needs deep excavation, shoring and full waterproofing, and may need dewatering. It is priced separately and can approach the cost of the whole villa structure.
Outdoor worksThe boundary wall, gate, underground tank, septic tank, yard paving and shades. They are usually built during the structure stage but sit outside the rate per metre, and each has its own reference in the calculator.
Design, supervision and permitThe engineering office's fees for design and supervision, the building permit, insurance and temporary utility connections, and the soil investigation.
VATThe published reference does not state its tax basis, so the figures here exclude VAT. If the contractor quote excludes it, add 15%.
The structure with what is usually built alongside it
Most owners building a structure order the boundary wall, the underground tank and the septic tank in the same stage, since the equipment and excavation are already on site. A worked example for a 400 m² villa:
Item
Example
Range
Villa structure
400 m² with materials and labour
SAR 220k – 300k
Site fence
Block boundary wall, 80 m long, 3 m high
SAR 21k – 21k
Water tank
Concrete tank, about 24 m³
SAR 15k – 20k
Septic tank
Medium concrete septic tank
SAR 7k – 10k
Total
Structure with the basic site works
SAR 263k – 351k
Basement and its works
150 m² basement, ordinary ground
SAR 180k – 225k
Basement and its works
150 m² basement, groundwater
SAR 270k – 330k
The gate, yard paving, shade, pool and lift are in the full villa cost guide. The basement on ground with groundwater excludes dewatering during excavation and perimeter drainage.
Structure by building type
Villa650 SAR/m² on average SAR 550 – 750/m²
Duplex650 SAR/m² on average SAR 550 – 750/m²
Rest house or chalet650 SAR/m² on average SAR 550 – 750/m²
Residential building720 SAR/m² on average SAR 610 – 830/m²
Duplexes and chalets take the villa rate because their frame is similar. An apartment building is higher because it has more floors, loads and services and needs heavier foundations and columns. Commercial buildings and warehouses have different references in the calculator.
Riyadh compared with other regions
The calculator builds regional rates on the Riyadh reference plus each region's published 2026 difference. The structure of a 400 m² villa in each region:
Region
Structure of a 400 m² villa
Rate per m²
Riyadh
SAR 220k – 300k
SAR 550 – 750/m²
Jeddah
SAR 228k – 308k
SAR 570 – 770/m²
Eastern Province
SAR 224k – 308k
SAR 560 – 770/m²
The regional differences are small; what really moves the figure is the design, the soil and the contractor, not the city.
What raises or lowers the structure rate?
Steel and cement pricesSteel and concrete are the two largest items in the structure, and any move in their prices shows up directly in contractor quotes. That is why the calculator shows a range with a review date rather than a fixed number.
Structural designWide column-free spans, double-height spaces, projections and cantilevers increase the steel, the slab thickness and the formwork cost. A regular plan on a simple column grid is cheaper.
SoilWeak or rocky soil or shallow water means deeper foundations, a raft, or excavation with special equipment. A soil investigation before contracting protects the figure from surprises.
Heights and number of floorsA ceiling higher than usual adds blocks and columns. A third floor needs heavier columns and foundations, so the structure rate for three floors is slightly higher than for two.
References used
The calculator computes the figures from published Saudi references and keeps each item's reference and last review date. The references behind the figures on this page:
Published references from contractors and specialist sites, not an official price list. The quote from a contractor who has seen your drawings and your site is the figure to build on.
What does a square metre of structure cost in Riyadh in 2026?About SAR 550 – 750/m² with materials and labour for an ordinary new villa, per the published reference the calculator uses. A contractor who sees the drawings and the site may quote lower or higher depending on design and soil.
What does the structure price include?Ordinary excavation, foundations, columns, slabs, stairs and block walls, with materials and labour, up to the roof annex. It excludes the basement or special excavation, the boundary wall and outdoor works, and every finishing item such as plaster and insulation.
Are plaster and insulation part of the structure?In the Saudi market plaster and insulation are usually counted with finishing, not with the structure, and that is how the calculator counts them. Some contractors include roof insulation or façade plaster in a structure quote, so ask explicitly before comparing quotes.
How much is the structure of a 400 m² villa?About SAR 220k – 300k for a 400 m² villa in Riyadh, or SAR 550 – 750/m². That is roughly 35% of a full build at the standard level; the rest is finishing.
Does the structure rate differ between a villa and an apartment building?Yes. The calculator uses about SAR 610 – 830/m² for an apartment building against SAR 550 – 750/m² for a villa, because it has more floors, loads and services. Duplexes and chalets take the villa rate.
How much does a basement add to the structure?A 150 m² basement on ordinary ground is about SAR 180k – 225k, and on ground with groundwater about SAR 270k – 330k, excluding dewatering and perimeter drainage. A basement can approach the cost of the whole villa structure, so do not decide on it before a soil investigation.
Do the prices include VAT?The published reference does not state its tax basis, so the calculator shows the figures without VAT and says so. If the contractor quote excludes VAT, add 15%.
Materials and labour, or labour only?The figures here are with materials and labour. A labour-only contract where you buy the steel, cement and blocks lowers the contract figure on paper, but moves procurement and price risk to you. Compare the two offers on the same scope before comparing the number.
Price your own structure
In the free calculator choose “structure only”, enter your city and area, and add the basement, wall or tank if you want; it gives you the range with what it covers and what a contractor quote must confirm, with no sign-up. For the full build with structure and finishing see the guide to the cost of building a villa in Riyadh.