Quantity take-off from drawings step by step

Quantity take-off turns what you see on the sheets into numbered items, each with a unit of measurement, a quantity and a calculation basis that someone else can check. The order that produces the fewest errors is the order of construction itself: excavation and foundations, then the concrete frame, then masonry, then plaster and insulation, then floors, ceilings and paint, then doors and windows, then plumbing and electrical. A take-off without a measurement record showing where every figure came from is a figure without evidence, even when it is right.

This guide is for the engineer in an engineering office or contracting company who receives architectural and structural drawings and is asked for a bill of quantities. It explains what you need before you start, the order, the unit of every item and the deduction rules, then a worked example from a villa, and finally how the same thing is done on screen.

What you need before the first figure

  1. Complete sheets at a known scale. Floor plans for every storey, sections, elevations, the door and window schedule, and the structural sheets for foundations, columns and slabs. A plan alone is not enough to take off concrete, and a section alone is not enough to take off flooring.
  2. Checking the scale. Measure a written dimension on the sheet and compare it with the measurement on paper or on screen. A PDF sheet printed "fit to page" loses its scale, and many take-off errors begin here.
  3. A list of items before measuring. Write down the items you will take off, in order and with their units, before you measure anything. Measuring first and classifying later produces duplicated items and forgotten ones.
  4. A measurement record. A sheet or table recording for every item: the drawing sheet, the position, the dimensions, the calculation and the result. This record is what makes the take-off reviewable, priceable and claimable later.

Agreed units of measurement

ItemUnitNote
Excavation and backfillm³Footing dimensions plus the usual working space
Plain and reinforced concretem³Footings, neck columns, ground beams, columns and slabs each separately
Reinforcement steeltonne or kgFrom the bar schedules, not from an assumed ratio except for a preliminary estimate
Blockworkm²Net after deducting openings, by thickness
Plasterm²Two faces for an internal wall, one face for an external wall
Flooring and tilesm²Net internal area of the room after plastering
SkirtinglmRoom perimeter minus door widths
Paintm²As flooring for ceilings, as plaster for walls
Doors and windowsCountFrom the schedule, verified on the plan
Stairslm for treads and risers, m² for the stair surfaceTaken off from the detail sheet, not the plan
Aluminium and facadesm² or lm for the frameAccording to the contracting method

The unit is not a formality. A blockwork item in linear metres or by count cannot be priced from a price catalogue that works in square metres, and it confuses the comparison of supplier offers.

The order: from the ground to the roof, then from outside to inside

1. Excavation and foundations

Start from the structural foundation sheet. For every footing: length × width × depth from the structural schedule, then group identical footings into one item with their count. Excavation is taken off as the footing dimensions plus working space on every side according to depth, and backfill is the excavation volume minus the volume occupied by the construction. Plain concrete under footings is a separate item by its thickness.

2. The concrete frame

Neck columns and ground beams from the structural sheet by their net length between footings. Columns: column section × height from ground-beam level to the slab soffit, multiplied by their count on each floor; columns of different sections are separate items. Slabs: slab area × thickness, deducting large openings such as the stairwell and light well. Drop beams are taken off only for what exceeds the slab thickness, so they are not counted twice. Reinforcement is taken off from the bar schedules on the structural sheets for every element; an assumed ratio per cubic metre is fine for a preliminary estimate, not for a quotation.

At this stage you have the "shell" quantities, which is what the cost of shell construction in Riyadh page covers with prices.

3. Masonry (blockwork)

For every wall: length from the plan × net height from the section (from floor level to the soffit of the slab or beam), then deduct openings. The rule customary in the market deducts in full every opening larger than half a square metre, and the rule in the specification adopted by the contract is followed where it says otherwise. External walls of 20 cm and internal walls of 10 or 15 cm are separate items because their prices differ. Do not forget the roof walls, the annex and the parapet; they are the most often forgotten.

4. Plaster and insulation

Plaster is two faces for internal walls and one external face for external walls; openings are deducted by the same rule, but the reveals of openings are added where the walls are thick and the specification requires it. Ceiling plaster equals the net ceiling area. Waterproofing of roofs and bathrooms and thermal insulation of external walls are separate items in square metres.

5. Floors, ceilings and paint

Flooring comes from the net internal dimensions of every room. In the published example from the twin-villa test: a master bedroom with internal dimensions of 4.000 × 3.250 m gives 13.00 m², the figure verified by two independent readings and matching the area printed on the sheet. Skirting is the room perimeter minus door widths. Suspended and gypsum ceilings take only the area of the rooms stated on the ceiling sheet. Paint for ceilings is the ceiling area, and for walls the internal plaster area minus what another cladding will cover, such as ceramic tiles in bathrooms and kitchens.

6. Doors, windows and aluminium

Counted from the door and window schedule, then matched on the plan symbol by symbol. Counting from symbols alone without a schedule is a visual count that needs confirmation. In the twin-villa test the item "door rated STC 30 for sound insulation" came out as 10 with the status "Review" because it was counted from symbol circles rather than from a schedule, and that is exactly what should happen: the figure stays in front of you with the reason for doubt instead of being hidden. Aluminium frames are taken off in linear metres from the perimeter: unit ALUM-14 for the terrace door, 1.00 × 3.42 m, gives 2 × (1.00 + 3.42) = 8.84 lm.

7. Stairs

From the stair detail sheet, not the plan. Riser cladding in linear metres: 22 steps × 1.00 m width = 22.00 lm, checking that the level difference (3.80 m in the example) equals the number of steps × the riser height. Treads the same way, and the concrete stair slab in cubic metres under the concrete item.

8. Plumbing and electrical

For a preliminary estimate these are taken off as points: one plumbing point per fixture and one electrical point per outlet, from the electrical and plumbing sheets. For a construction quotation the pipes are detailed in linear metres and the fixtures by count. This part is often put in a separate bill of quantities handed to the subcontractor.

Deduction rules that ruin a take-off when ignored

Worked example: one room of a villa

A master bedroom with internal dimensions of 4.00 × 3.25 m and a clear height of 3.20 m, with a door of 1.00 × 2.20 m and a window of 1.60 × 1.40 m. External walls 20 cm, internal walls 15 cm (two walls of each kind). This is how the measurement record looks:

ItemCalculationQuantity
Porcelain flooring4.00 × 3.2513.00 m²
Skirting2 × (4.00 + 3.25) − 1.0013.50 lm
External blockwork 20 cm (two walls)(4.00 + 3.25) × 3.20 − window 2.2420.96 m²
Internal blockwork 15 cm (two walls)(4.00 + 3.25) × 3.20 − door 2.2021.00 m²
Internal wall plasterperimeter 14.50 × 3.20 − (2.24 + 2.20)41.96 m²
Ceiling plaster4.00 × 3.2513.00 m²
Wall paintAs internal plaster41.96 m²
Ceiling paintAs ceiling plaster13.00 m²
doorFrom the schedule, symbol D-03 on the plan1 no.
Aluminium windowFrom the schedule, symbol W-071 no.

Two notes in the record: the external plaster of the two external walls is taken off under the facades item at villa level, not room level, and the blockwork of the two internal walls is shared with the adjacent rooms, so it is taken off once at floor level. These two cautions are the difference between taking off a room and taking off a building: the building is taken off by floor and by facade, and the room is a unit of verification, not a unit of take-off.

Note: the figures in this example are an exercise calculated on the room dimensions published from the twin-villa test, not a complete test result. The other dimensions (height and openings) are assumed for illustration.

How long a manual take-off takes, and where the time goes

A villa of seven architectural sheets takes an experienced engineer one to three working days by hand, depending on the detail required. Most of the time goes not to measuring but to three things: moving between sheets to link the plan, the section and the schedule; writing the measurement record; and self-checking. These three are what the app can shorten.

The same thing on screen

In KAM Estimator desktop app in the published release 0.15.224, the takeoff path follows the same order, but the sheet and the record are in one place:

  1. Open the file PDF, DWG or DXF directly at its true scale; a DWG file is converted into sheets on your computer and the original file is not sent to any server.
  2. Know the cost before you start: the app divides the sheets into stages and shows the maximum number of points before a single point is deducted.
  3. Two independent readings of each stage: the sheets are read twice separately and the two results are merged. Agreement gives a "Confirmed" item; disagreement or a visual count gives a "Review" item that stays in front of you with its note.
  4. Every item carries its calculation basis and its position on the sheet: the last column of the bill of quantities is the measurement record itself, written as the app wrote it: the dimensions, the operation, the sheet and the symbol.
  5. Manual take-off on the drawing for what you want to measure yourself: a Revit-style toolbar, "pick lines" to build the room from the drawing lines, automatic deduction of openings, and linear, arc, radius and angle dimensions. In DWG and DXF files it reads blocks, hatches and the door and window schedule, and hidden layers are not counted.
  6. Export or hand over: the bill of quantities to Excel, or a PDF with the items marked on the sheets, or the "Hand over to pricing" button, which moves the project with its quantities to the pricing path to produce a quotation with your logo.

In the published twin-villa test, 131 items came out in 31 minutes over three stages, and the flooring areas of 41 rooms differed from the reference manual take-off by −2.5%. An internal test result, not a guarantee, and every item in it carries its calculation basis so you can verify it yourself.

Checklist before approving the bill of quantities

References

  1. Saudi Building Code (Saudi Building Code National Committee) · The requirements that govern thicknesses and insulation, checked
  2. RICS New Rules of Measurement (NRM) · Measurement rules and the deduction of openings, checked
  3. International Cost Management Standard (ICMS) · Classification of items and international measurement methods, checked

FAQ

What is the difference between quantity take-off and a bill of quantities?Quantity take-off is the process of measuring from the sheets; the bill of quantities (BOQ) is its result, arranged into items with a unit and a quantity, and it becomes a priced estimate once prices are added. Some offices call the whole process "measurement" or "quantity calculation".
Do I take off from the architectural or the structural drawings?From both. Concrete, reinforcement and foundations come from the structural set; walls, finishes and openings from the architectural set; heights from the sections. Taking off from the architectural set alone misses the shell, and from the structural set alone misses the finishes.
How do I deduct openings from blockwork?The common rule deducts in full every opening larger than half a square metre, applying the same rule to plaster and paint. If the contract or specification sets another rule, that rule takes precedence.
Do I calculate flooring from the floor area?No. Flooring comes from the net internal area of each room after plastering. The external floor area includes the walls, and in a 400 m² villa the difference can reach tens of square metres.
What is a measurement record and why does it matter?A record for every item showing the sheet, the position, the dimensions and the calculation. It is how the take-off is reviewed, how disputes with the contractor or the owner are settled, and how a quantity is updated when the drawing changes. A bill of quantities without a measurement record cannot be verified.
How long does a manual villa take-off take?One to three working days for a medium villa depending on the level of detail, with most of the time spent moving between sheets, writing the record and reviewing. In the published test of the app, a twin villa of seven sheets took 31 minutes with a calculation basis for every item.
Does the app read DWG files directly?Yes. It opens DWG, DXF and PDF directly at their true scale; DWG is converted into sheets on your computer; it reads blocks, hatches and the door and window schedule, and hidden layers are not counted.

Try the take-off on your drawing

Download the app with a free 14-day trial, 150 points of credit and no card.

Try the take-off on your drawing

This guide was published on . The prices mentioned are examples from published references with their dates, not a quotation.