Kamyeklaf

Cost guide · Riyadh 2026

كم يكلف بناء عمارة 600 م في الرياض؟

Figures from the Kamyeklaf calculator engine itself, built on published Saudi references for 2026, for a residential building with structure and finishing. A planning estimate, not a contractor quote, and every figure here can be recalculated by you in the free calculator.

The short answer

In the market, a “600 m building” usually means a building on a 600 m² plot. At a 60% coverage ratio the floor plate is about 360 m², and a ground floor, two upper floors and a roof annex add up to about 1,200 m². At a standard finish this building costs in Riyadh about SAR 1.87M – 2.8M, that is SAR 1,560 – 2,330/m². The structure with materials is about SAR 732k – 996k, and the finishing about SAR 1.14M – 1.8M.

If what is meant is a small building with 600 m² of floor area in total (two floors of about 300 m² each), the figure is about SAR 936k – 1.4M at the standard level. The gap between the two figures is the gap between plot area and built area, and it is the most common mistake made when asking about cost.

Cost by total floor area and finish level

Total floor areaEconomyStandardPremiumSuper lux
600 m²720k – 996k936k – 1.4M1.28M – 1.95M1.8M – 2.36M
900 m²1.08M – 1.49M1.4M – 2.1M1.92M – 2.93M2.7M – 3.54M
1,200 m²1.44M – 1.99M1.87M – 2.8M2.56M – 3.9M3.6M – 4.72M
1,500 m²1.8M – 2.49M2.34M – 3.5M3.2M – 4.88M4.5M – 5.9M

Figures in SAR for a complete build (structure and finishing), including materials and labour. They exclude land, design, supervision, the lift, air conditioning, kitchens and VAT. The “standard” level is the most requested for residential and rental buildings.

How much building does a 600 m plot carry?

What counts is the total built floor area, which is set by the district's building code (coverage ratio and permitted floors), not by your wishes alone. These are the common configurations for a 600 m² plot in Riyadh, all at the standard level:

600 m²A small two-floor building of about 300 m² per floor: two large apartments or four small ones. Suits a narrow plot or a low coverage ratio.Full build, standard: SAR 936k – 1.4MStructure: SAR 366k – 498k · Finishing: SAR 570k – 900kEconomy: SAR 720k – 996k · Premium: SAR 1.28M – 1.95M
900 m²Ground plus two floors of about 300 m² each, or two floors and a roof annex on a 360 m² plate. About 4 to 6 apartments.Full build, standard: SAR 1.4M – 2.1MStructure: SAR 549k – 747k · Finishing: SAR 855k – 1.35MEconomy: SAR 1.08M – 1.49M · Premium: SAR 1.92M – 2.93M
1,200 m²The most common configuration on a 600 m² plot: ground plus two floors on a plate of about 360 m² and a roof annex of about 120 m². About 6 apartments with a lift and parking.Full build, standard: SAR 1.87M – 2.8MStructure: SAR 732k – 996k · Finishing: SAR 1.14M – 1.8MEconomy: SAR 1.44M – 1.99M · Premium: SAR 2.56M – 3.9M
1,500 m²Ground plus three floors on a 360 m² plate and an annex, where the code allows four floors. About 8 apartments, and the lift and protected stairs become a requirement, not an option.Full build, standard: SAR 2.34M – 3.5MStructure: SAR 915k – 1.25M · Finishing: SAR 1.43M – 2.25MEconomy: SAR 1.8M – 2.49M · Premium: SAR 3.2M – 4.88M

Per floor: each 360 m² floor at the standard level costs about SAR 562k – 839k for structure and finishing. This is the figure that helps when weighing two floors against three, remembering that the foundations, the lift and the roof do not multiply with the floors.

Price per metre at each level

Economy1,430 SAR/m² on average
SAR 1,200 – 1,660/m²
Standard1,950 SAR/m² on average
SAR 1,560 – 2,330/m²
Premium2,690 SAR/m² on average
SAR 2,130 – 3,250/m²
Super lux3,470 SAR/m² on average
SAR 3,000 – 3,930/m²
EconomyA rental building with practical materials: local porcelain tiles, pressed doors, plumbing and electrical work to the required minimum, a simple entrance. Suits those building to let who want the fastest return.
StandardThe most requested: higher-grade porcelain, marble in the lobbies and stairs, better doors, concealed lighting in the living rooms, a facade with reasonable detailing. This is the level the figures in this guide are based on.
PremiumApartments for sale or family living: more marble, detailed joinery, sanitary ware from known brands, a high-finish lobby and lift. Most of the increase is in the finishing, not the structure.
Super luxImported materials and full interior design for the apartments and lobbies. Quotes vary widely from one contractor to another, and the range is only a starting point for planning.

Structure only or turnkey?

The “structure” is the excavation, foundations, concrete frame and masonry from the footings to the annex roof, with materials and labour. The “finishing” is everything that makes the apartments habitable: plastering, floors, ceilings, paint, doors, plumbing and electrical work. “Turnkey” has no single definition; with some contractors it includes the boundary wall, parking, water tank and septic tank, with others it does not. Always ask what the quote includes item by item, and see the Riyadh structure cost guide for details of what the structure includes.

Stage1,200 m² building, standardWhat it covers
Structure with materialsSAR 732k – 996kExcavation, foundations, the concrete frame and ordinary masonry. Excludes the lift shaft and its equipment and the external works.
FinishingSAR 1.14M – 1.8MPlastering, insulation, floors, ceilings, paint, doors, plumbing and electrical work for the apartments and lobbies.
The whole buildingSAR 1.87M – 2.8MStructure and finishing together, which is what the first table shows.
The usual outdoor worksSAR 95k – 135kA 100 m boundary wall, two electric gates, a large water tank, a large septic tank, 200 m² of parking paving, 60 m² of canopies. Each item with its size in the next table.
LiftSAR 95k – 185kA four-stop lift, supplied and installed. Its shaft and machine room are part of the structure if designed in from the start.
Turnkey in the broad senseSAR 2.06M – 3.12MThe complete building with the lift and the usual external works.

The structure is about 37% at the standard level, and it falls as the level rises because it is the finishing that grows. Many building owners build the structure and then finish floor by floor as they let; this spreads the payments but raises the total slightly through price changes and setting up the site more than once.

How much do the extras add?

Extras are not priced per square metre of the building; each is priced by its own size and reference. This is a worked example for a 1,200 m² building on a 600 m² plot with the sizes stated; change the sizes in the calculator and the figure changes.

ExtraExampleRangeReference
Site fence100 m block wall, 3 m highSAR 26kaismartprompts.com
GatesTwo electric car gatesSAR 15k – 26kmakkahexperts.com
Water tankLarge underground water tankSAR 23k – 32kalmaal.org
Septic tankLarge concrete septic tankSAR 10k – 14kalmaal.org
Courtyard paving200 m² of interlock paving for parking and yardSAR 14k – 22kscbm.sa
Canopy or screen60 m² of car canopiesSAR 7k – 16kzilriyadh.com
LiftFour-stop liftSAR 95k – 185kswiftlifts.com

Three items belong to a building but not a villa and do not appear in the per-metre price: Lift (with its shaft in the frame),parking which the code requires according to the number of apartments and may mean a full basement in some districts, andsafety requirements from a protected stair and fire doors to alarm and fire-fighting systems depending on the number of floors. The basement in particular depends on the soil and groundwater, so do not rely on its figure before a site investigation.

What makes up the cost?

For a 1,200 m² building at the standard level, this is how the amount splits by calculator item:

ItemRangeOf the total
Structure with materials — Riyadh732k – 996k37%
Interior finishing — Riyadh1.14M – 1.8M63%

What raises or lowers the figure?

Floor area, not plot areaThe calculation is on the total floor area. A 600 m² plot carries 600 or 1,500 m² of building depending on the coverage ratio and the number of floors, and the difference between the two figures is more than double.
The levelMoving from standard to premium raises the cost by about 38%, mostly in the finishing of the apartments, the lobby and the facade.
Number and layout of apartmentsMore apartments on the same plate mean more kitchens, bathrooms, doors and meters, so the finishing metre goes up. Two apartments per floor cost less than four on the same area.
Lift, parking and safetyItems that are not in the per-metre price, appear in a building but not a villa, and grow with the number of floors. Ask for them item by item in the contractor's quote.
The market and timingPrices come from the published 2026 references and move with steel, cement and labour prices. A range, not a single figure, is the honest way to plan.
Contract typeAn all-in quote with materials spares you the follow-up but puts the price risk on the contractor, so the figure goes up. A labour-only contract with you buying the materials is lower on paper and needs time and knowledge of the market.

What these figures leave out

These items are outside every figure in this guide and are added on top when planning: the land price and transfer fees, architectural and structural design and the engineering office's supervision, the building permit, insurance, utility connections and electricity and water meters for each apartment, air-conditioning units and their piping, kitchens with cabinets, furniture and decorative lighting, and VAT. The free calculator shows some of these as optional extras with their reference when one is available.

References used

The figures in this guide are computed by the calculator from published Saudi references, and each item keeps its reference and the date it was last checked. These are the references used for the figures on this page:

  1. asiabuildings.sa · Structure with materials — Riyadh, checked
  2. mashatib.com · Interior finishing — Riyadh, checked
  3. aismartprompts.com · Site fence, checked
  4. makkahexperts.com · Gates, checked
  5. almaal.org · Water tank, checked
  6. swiftlifts.com · Lift, checked
  7. scbm.sa · Courtyard paving, checked
  8. zilriyadh.com · Canopy or screen, checked

These are published references from contractors, suppliers and specialist sites, not an official price list. The differences between sources are why a range is shown, and the quote from a contractor who has seen your drawings and your site is the figure to build on.

Read also

How much does it cost to build a villa in Riyadh in 2026?The same figures for villas of 300 to 600 m² at four levels.
cost of shell construction in RiyadhThe price per metre and what the structure includes, item by item.
Contractor quotation template with a bill of quantitiesWhat the offer you receive from the contractor must contain.

FAQ

How much does an apartment building on a 600 m² plot cost in Riyadh in 2026?A 600 m² plot usually carries a building of about 1,200 m² of floors (ground, two floors and a roof annex at 60% coverage). At the standard level that is about SAR 1.87M – 2.8M for structure and finishing, or SAR 1,560 – 2,330/m². The structure alone is about SAR 732k – 996k.
And if the building itself is only 600 m² of floors?A small building of 600 m² of floors (two floors of about 300 m² each) costs about SAR 936k – 1.4M at the standard level. The estimate is always on the sum of built floors, never on the plot.
What does a square metre of apartment-building construction cost in Riyadh?About SAR 1,560 – 2,330/m² at the standard level for structure and finishing. The per-metre figure is close to a villa because published references price the built metre; the real differences come from the lift, parking and safety requirements, which are priced separately.
How much is the structure alone?The structure with materials for a 1,200 m² building in Riyadh is about SAR 732k – 996k, or SAR 610 – 830/m². It covers excavation, foundations, the concrete frame and masonry; the lift and outdoor works are separate.
How much does a lift add?A four-stop lift in the worked example here adds about SAR 95k – 185k on top of the building. It needs a shaft in the structure from the design stage.
Do the figures include VAT?No. The published references do not state their tax basis, so the calculator shows figures without VAT and says so. Add 15% to a quote that excludes it.
What separates the standard level from premium in a building?For a 1,200 m² building, moving from standard to premium raises the cost by about 38%, mostly in the finishing of the apartments, lobbies and facade, not in the concrete frame.
Are these figures a contractor quote?No. They are planning estimates from published 2026 references. An execution quote comes from a contractor who has seen the drawings and the site, which is why the calculator gives a range.

Price your own building

The free calculator takes your city, floor areas, finish level and extras (lift, boundary wall, parking, tank) and gives you the range with what it includes and excludes, with no sign-up. For those who have the building's drawings, KAM Estimator takes off the quantities from the drawing itself and produces a priced bill of quantities.

Open the free calculatorRequest a contractor referral in Riyadh