Guide · Pricing
BOQ pricing: unit-rate analysis step by step
The price of any item in a quotation is the sum of five layers: materials including waste, labour, equipment, then the item's share of indirect costs, then profit, and finally VAT, which is shown separately. The contractor who writes "1,200 riyals per cubic metre" because it is the usual market figure makes or loses money by chance. The contractor who breaks the figure into its layers knows where to give ground in competition and where to stop. This guide explains the method, then applies it in full to one cubic metre of reinforced concrete at published Saudi market prices.
The guide assumes the bill of quantities is ready in your hands, whether it came from the engineering office or you took it off yourself as in the Guide to quantity take-off from drawings.
Before pricing: clean the bill
Three minutes here save hours later:
- Units. Make sure every item is in its customary unit: concrete in cubic metres, blockwork and plaster in square metres, skirting in linear metres, doors by count. An item in an odd unit cannot be priced from a catalogue or compared with a supplier's offer.
- Specification. "Reinforced concrete" alone is not enough for pricing. Grade 250 or 350? Slabs or footings? Is the reinforcement within the item or a separate item? Each of these questions changes the price by tens of percent.
- Missing items. A large share of contractors' losses comes from items that were never in the bill: steel formwork at height, concrete pumping, laboratory tests, site cleaning. Add them as items or put them into indirect costs, but do not leave them hanging.
The five layers of an item price
1. Materials
The purchase price plus transport to site and waste. Waste is not a random allowance but a known percentage for each material: about 5% for ready-mix concrete, 3 to 5% for reinforcement depending on cutting, and 5 to 10% for blocks and tiles. The quantity of material per unit of the item is calculated from consumption rates: how many kilograms of steel per cubic metre, and how many square metres of formwork a cubic metre of this element needs.
2. Labour
The crew's daily wage divided by its daily productivity in the item's unit. A carpentry crew with a known daily wage completes a known number of square metres of formwork a day, and the division gives the wage per square metre. Productivity is taken from the records of your previous projects, the most valuable information a contractor owns.
3. Equipment
The rental or daily depreciation of the machine divided by its productivity: the concrete pump per cubic metre, the crane per hour, the small mixer per day. What is rented by the metre, such as the pump, is entered directly; what is owned is calculated by depreciation and running cost.
The sum of the three layers is the direct cost of the item, which is what executing it on site actually costs you.
4. Indirect costs
What cannot be attributed to a particular item: the site engineer and supervisor, the site office, electricity and water, insurance and bank guarantees, labour transport and housing, tests, and the project's share of head-office expenses. They are totalled for the whole project and then distributed over the items as a percentage of their direct cost. In villa projects the percentage usually falls between 10 and 15%, varying with the project's size, duration and location, and you must calculate it from your project's budget, not from a common figure.
5. Profit
A percentage of the total direct and indirect cost. This alone is where competition happens: the contractor who knows the true cost lowers profit deliberately to win a project they need, and does not go below zero without knowing.
6. Value-added tax
Calculated on the selling price at 15% and shown in the quotation separately from the item price. Putting it inside the unit price confuses a client comparing offers, some inclusive and some not.
Worked example: one cubic metre of reinforced concrete for a villa slab in Riyadh
The item: reinforced concrete for a hollow-block or solid slab, grade 300, including reinforcement, formwork and pouring, per cubic metre. The prices below are of two kinds, and they must be distinguished: published market prices with their sources, and productivity and rate assumptions which every contractor replaces with their own figures.
Materials
| Material | Rate per cubic metre | Price | Source | Cost |
|---|---|---|---|---|
| Ready-mix concrete grade 300 | 1.00 m³ + 5% waste = 1.05 | 280 SAR/m³ | Msamer blog 2026: grade 250 between 220 and 280, grade 350 between 280 and 350; 280 adopted for grade 300 (an assumption within the published range) | 294 |
| Reinforcement steel | 100 kg for the slab + 4% waste = 104 kg | 3.00 SAR/kg (3,000 SAR per tonne) | Msamer blog 2026: 2,800 to 3,200 SAR per tonne | 312 |
| Formwork timber and accessories | 6 m² of formwork per m³ of slab (rate) | 25 SAR/m² share of one use | Assumption, to be replaced with your supplier's price | 150 |
| Wire, spacers and small materials | Assumption | 15 | ||
| Materials total | 771 |
The rate of 100 kg of steel per cubic metre is a common estimating rate for slabs; the correct figure is taken from the bar schedules on the structural sheets as in the take-off guide. 6 m² of formwork per cubic metre suits solid slabs about 17 cm thick and differs greatly for columns and beams.
Labour and equipment
| Item | Basis | Cost |
|---|---|---|
| Formwork carpentry | 6 m² × 20 SAR/m² (crew wage ÷ productivity, assumption) | 120 |
| Steel fixing | 0.104 tonne × 350 SAR/tonne (assumption) | 36 |
| Pouring and curing | 40 SAR/m³ (assumption) | 40 |
| Concrete pump | 15 SAR/m³ from the pump price ÷ pour quantity (assumption) | 15 |
| Labour and equipment total | 211 |
From cost to quotation price
| Layer | Calculation | SAR/m³ |
|---|---|---|
| direct cost | 771 + 211 | 982 |
| Indirect costs | 12% × 982 | 118 |
| Total cost | 1,100 | |
| Profit | 10% × 1,100 | 110 |
| Item price in the quotation | 1,210 | |
| Value-added tax | 15%, shown separately | 182 |
| What the client pays | 1,392 |
The figure of 1,210 riyals per cubic metre is not a price we recommend but the result of these particular assumptions. Replace any figure marked "assumption" with your own and the result will move. That is the point: when a contractor competes with you at 1,050 riyals, you know they either have higher productivity, buy steel cheaper, accept less profit, or did not calculate something, and you decide on that basis.
What moves the price more than anything else
- The steel price alone is about a quarter of the direct cost in slabs, and more in columns. The price per tonne changes monthly, so date your quotation and set its validity period.
- The formwork rate varies from 4 m² per cubic metre in a raft to 12 and more in slender columns, which is why pricing concrete as one item for all elements is a common mistake.
- The pour size determines the pump share per metre and the minimum delivery, so an 8-metre pour costs more per metre than an 80-metre pour.
- Indirect costs are calculated from the project duration, so a two-month delay adds the engineer's and office wages onto the same items.
Recurring pricing mistakes
- Pricing by the flat metre for the whole building and then distributing it over the items. Fine for a preliminary estimate for the owner, not for a construction quotation.
- Copying prices from a previous quotation without updating steel, concrete and labour.
- Waste twice: in the material rate and in the general contingency percentage.
- Tax inside the unit price and then adding it again in the total.
- Profit on the direct cost only while forgetting that indirect costs are a cost too.
- A price without a source and date. When the client asks two months later why the price went up, you have nothing to show them.
The same thing on screen
In the pricing path of KAM Estimator desktop app in the published release 0.15.224, the same steps run directly on the bill of quantities:
- Open the bill of quantities from new or old Excel as it is, with its items, units and quantities, or from a PDF read as printed with symbol, description, unit and quantity at a quarter of a point per page; the client's bill comes in complete with its text verbatim.
- Clean the bill by dragging, sorting, copying and deleting with undo before you price anything.
- Price from three sources: your price library saved on your computer with automatic matching of items, or your suppliers' offers imported from PDF and images after "request a quotation", or Saudi market prices with their published sources and dates. Every priced item has "compare with the market" to see where your price stands, and the source and date of every price stay with the item.
- Produce the quotation as PDF and Excel with your logo and the final prices, without showing cost and profit to the client, with versions, follow-up and a template designer.
- Save your prices: when you issue the quotation the app asks whether you want to save the prices you wrote into your library, so the next quotation is faster, and you can share the library with another computer by merging.
The column that carries the source and date of the price is what solves the sixth mistake above, and the price library that grows from your quotations is what solves the second.
References
- Msamer blog: building-material prices in Saudi Arabia 2026 · Ready-mix concrete and reinforcement steel prices, checked
- Zakat, Tax and Customs Authority: guidelines · The VAT rate and how it is shown, checked
FAQ
Try pricing on your bill of quantities
Plans and the free 14-day trial with no card.
This guide was published on . The prices mentioned are examples from published references with their dates, not a quotation.